This is the longest full path on the project.
Critical path
Oops!
Okay!
What is total float?
Total float is the amount of time that a task can be delayed without delaying the project's overall completion date.
Oops!
Okay!
Add this type of time to the project schedule to account for unforeseen circumstances.
Contingency time.
Oops!
Okay!
Which of the following are required in regards to quality processes on a project:
Organizational quality policies
Policies
Standards
Regulations
Oops!
Okay!
What is free float?
Free float refers to the amount of time that a task can be delayed without delaying the start of the immediate successor task.
Oops!
Okay!
A critical path task is a task with which type of float?
Summed float
Total float
Free float
Zero float
Oops!
Okay!
This technique attempts to smooth out the resource assignments.
Resource leveling
Oops!
Okay!
Both PERT and the Three-Point estimate technique use all of the following estimates in their calculations except for which one?
Pessimistic
Least Likely
Most Likely
Optimistic
Oops!
Okay!
T/F. The PERT formula calculates the simple average of three estimates.
False. PERT calculates the weighted average of three estimates.