T/F. The PERT formula calculates the simple average of three estimates.
False. PERT calculates the weighted average of three estimates.
Both PERT and the Three-Point estimate technique use all of the following estimates in their calculations except for which one?
Least Likely
A critical path task is a task with which type of float?
Zero float