What is free float?
Free float refers to the amount of time that a task can be delayed without delaying the start of the immediate successor task.
What is total float?
Total float is the amount of time that a task can be delayed without delaying the project's overall completion date.
Which of the following are required in regards to quality processes on a project:
 
Regulations
 
Standards
 
Policies
 
Organizational quality policies
This technique attempts to smooth out the resource assignments.
Resource leveling
Add this type of time to the project schedule to account for unforeseen circumstances.
Contingency time.
This is the longest full path on the project.
Critical path
A critical path task is a task with which type of float?
 
Zero float
 
Total float
 
Summed float
 
Free float
Both PERT and the Three-Point estimate technique use all of the following estimates in their calculations except for which one?
 
Least Likely
 
Most Likely
 
Pessimistic
 
Optimistic
T/F. The PERT formula calculates the simple average of three estimates.
False. PERT calculates the weighted average of three estimates.