  • T/F. The PERT formula calculates the simple average of three estimates.
    False. PERT calculates the weighted average of three estimates.
  •  15
  • Both PERT and the Three-Point estimate technique use all of the following estimates in their calculations except for which one?
    Optimistic
    Pessimistic
    Most Likely
    Least Likely
  •  15
  • A critical path task is a task with which type of float?
    Summed float
    Total float
    Zero float
    Free float
  •  15
  • This is the longest full path on the project.
    Critical path
  •  15
  • Add this type of time to the project schedule to account for unforeseen circumstances.
    Contingency time.
  •  15
  • This technique attempts to smooth out the resource assignments.
    Resource leveling
  •  15
  • Which of the following are required in regards to quality processes on a project:
    Regulations
    Organizational quality policies
    Policies
    Standards
  •  15
  • What is total float?
    Total float is the amount of time that a task can be delayed without delaying the project's overall completion date.
  •  15
  • What is free float?
    Free float refers to the amount of time that a task can be delayed without delaying the start of the immediate successor task.