This estimating technique involves obtaining quotes for the work or services to be performed.
Resource cost rates
Oops!
Check
Okay!
Check
15
This is used to measure the actual project expenses against the budgeted expenses: __________ __________.
Cost baseline
Oops!
Check
Okay!
Check
15
T/F. Indirect costs are costs specifically associated with the work of the project.
False. Indirect costs are costs associated with the project but not directly related to the work of the project.
Oops!
Check
Okay!
Check
banana
Go to last place!
Oops!
gift
Win 15 points!
Okay!
gift
Win 25 points!
Okay!
banana
Go to last place!
Oops!
15
This estimating process technique establishes estimates for each activity and adds them all together to determine an estimate for the project.
Oops!
Show
Check
Okay!
Check
15
T/F The project plan is made up of all the documents produced in the planning processes and the project plan should be signed off by the project sponsor and key stakeholders.
True
Oops!
Check
Okay!
Check
thief
Give points!
5
10
15
20
25
magnet
Take 25 points!
Okay!
fairy
Take points!
5
10
15
20
25
lifesaver
Give 10 points!
Oops!
15
Add this to the project budget to account for unexpected expenses: _______ __________.
Contingency reserves
Oops!
Check
Okay!
Check
15
This estimating technique bases the estimate for the current project on a past project of similar size and scope:__________.